Update: Ugbo–Oghoye Road: Amuwa Blames Contract Disputes, Contractor’s Capacity for Three-Year Delay
By Exponent News, Akure, 11th November, 2026
Former NDDC board member urges commission to revoke contract if contractor cannot deliver, says political will key to completion
Barrister Benson Amuwa, a former commissioner representing Ondo State on the board of the Niger Delta Development Commission (NDDC), has attributed the prolonged delay in the construction of the Ugbo–Oghoye road project to unresolved disputes between the commission and the contractor, alongside concerns over the contractor’s capacity to execute the project.
Amuwa, who spoke on the circumstances surrounding the abandonment of the road project, disclosed that construction was initially halted by the NDDC following disagreements over the scope of work, the project’s take-off point and the extent of work already completed by the contractor.
He identified the contractor as Murano, an Italian company, and expressed reservations about its capacity to execute the project, saying concerns about its competence had existed from the inception of the contract.
According to him, the disagreement over the project’s starting point further complicated the situation, as the commission reportedly wanted the contractor to adopt a different take-off point despite the company’s claims that it had already commenced work from the originally agreed location.
Also read Ugho Oghoye road:Former NDDC Commissioner Enikuemehin Challenges Successors To Explain 15 year Delay https://exponentnews.com.ng/2026/11/09/ugbo-oghoye-road-former-nddc-commissioner-challenges-successors-to-explain-15-year-delay/
Amuwa explained that the contractor had received mobilisation funds before a subsequent NDDC management ordered the suspension of construction to evaluate the work already executed.
However, the management left office without resolving the outstanding issues, leaving the project stalled for approximately three years before the board on which he served assumed office.
He said the board subsequently took steps to address the challenges, including preparing a memo, inviting the contractor for discussions and examining its claims to determine how the project could resume.
Amuwa disclosed that the management eventually agreed to remobilise the contractor and give it another opportunity to demonstrate its capacity to complete the job.
He said the contractor returned to the site, received additional payments and commenced work, including construction of the bridge, which he described as a major component of the project.
The former NDDC board member, however, said the efforts were interrupted following the removal of the board during the administration of former President Muhammadu Buhari.
Amuwa also questioned the initial decision to award the contract to Murano, arguing that proper due diligence should have been conducted before the company was selected.
He, however, maintained that the immediate priority should be finding a lasting solution to the challenges preventing the completion of the road.
Speaking on the possibility of completing the project under the current administration, Amuwa expressed optimism, insisting that the project was achievable if the government demonstrated sufficient political commitment.
“Why can’t it be completed? Any administration can complete a project. The only thing required is the political will,” he said.
He further advised the NDDC to consider revoking the contract and awarding it to another competent contractor if the existing company was no longer capable of delivering the project.
Amuwa stressed that the Ugbo–Oghoye road project remained achievable, adding that the commission and the current administration must demonstrate the commitment required to bring it to completion.
The road project is of significant importance to the Ilaje riverine communities of Ondo State, where improved road infrastructure is expected to enhance transportation, economic activities and connectivity.