More Facts About NDDC’s Ugbo–Oghoye Road: Procurement Report Raises Questions Over Contractors’ Capacity and ₦19.5bn Adjusted Bid
12th, November, 2026
A procurement assessment of the proposed construction of the Ugbo–Oghoye Road, Phase One, has recommended further technical scrutiny of the preferred contractor, Moreno D.C. West Africa Plc, before the Niger Delta Development Commission (NDDC) proceeds with the project.
The assessment, contained in a document detailing the procurement process, stressed the need for the NDDC to establish the contractor’s capacity to successfully execute the project, given its magnitude and technical requirements.
According to the document, six contractors submitted bid documents for the project out of the 1,365 contractors pre-qualified by the NDDC.
It identified Messrs Eminad Nigeria Limited as the consultant engaged to undertake the engineering designs of the road project but observed that the company was not registered with the Council for the Regulation of Engineering in Nigeria (COREN), raising concerns about its eligibility to practise engineering in the country.
The assessment consequently urged the NDDC to ensure that all its consultants are registered with relevant professional regulatory bodies to enable them to take full responsibility for their designs and bills of engineering measurement and evaluation (BEME).
On the financial aspect, the document revealed that changes were made to the original scope of work and BEME submitted by the NDDC, including a reduction in Bill 1 from ₦277.5 million to ₦74.4 million and a reduction in contingency from 10 per cent to one per cent.
The adjustments reportedly reduced the original consultant’s estimate from ₦13.028 billion to ₦12.329 billion.
However, following arithmetic corrections by the Bureau of Public Procurement (BPP), the NDDC’s in-house estimate stood at ₦20.304 billion, compared with the initially recommended figure of ₦20.315 billion.
The document further showed that Fhomo Nigeria Limited emerged as the lowest bidder with ₦20.669 billion, but concerns were raised over its unusually low rates for critical construction materials and activities, including excavation, reinforcement and Grade 30 concrete.
It warned that the rates could expose the project to abandonment and subsequent requests for price variations.
Similarly, Pamekson Global Services Limited, which submitted the second-lowest corrected bid of ₦22.049 billion, and Trade Point Investment Limited, with the third-lowest bid of ₦22.334 billion, were also flagged over low rates for critical bridge construction components.
Meanwhile, Moreno D.C. West Africa Plc emerged as the fourth-lowest bidder, with a corrected bid of ₦31.647 billion.
Despite ranking fourth, the assessment described the company’s rates for key items as generally fair and realistic, adding that it represented the best value for the procurement.
Following the application of Moreno D.C. West Africa Plc’s rates to the revised BEME, the adjusted tender sum was put at ₦19.506 billion.
The document, however, emphasised that a contractor’s capacity to successfully execute a project remained fundamental, stressing that the NDDC and the BPP must ensure that projects meet required specifications and standards.
It consequently recommended that the NDDC establish a technical team comprising professionals from its departments and consultants to physically inspect and verify the company’s plant holdings, yards, completed and ongoing projects, as well as its professional workforce.
The team is expected to submit a report for further review before the project proceeds.
The assessment warned that with dwindling resources from oil, the Niger Delta region and Nigeria could no longer afford failed projects, particularly one of such magnitude as the Ugbo–Oghoye Road.
Exponent News , Nigeria.