NDDC Ugbo–Oghoye Road Project: The Last Straw That Breaks the Camel’s Back
By Exponent News, Akure
November 16, 2026
Historical documents have revealed a series of contractual developments, technical assessments, disagreements and political interventions surrounding the long-delayed Ugbo–Oghoye Road project in Ilaje Local Government Area of Ondo State, dating back to 2009.
The revelations, contained in official correspondence, technical assessment reports, historical photographic records and letters from traditional authorities, provide fresh insight into the circumstances surrounding the conception, contractor selection and eventual flag-off of the strategic road project.
The documents indicate that the Niger Delta Development Commission (NDDC), on November 5, 2009, approved the award of the contract for the construction of the first phase of the Ugbo–Oghoye Road to Setraco Nigeria Limited at the sum of ₦19,409,143,685.70, with a completion period of 36 months.
However, Setraco subsequently rejected the offer, citing its inability to accept the contract without receiving essential contractual documents, including the scope of works, Bill of Quantities and project drawings.
2NDDCletter
In a letter dated December 7, 2009, addressed to the Managing Director of the NDDC, Setraco’s Managing Director, Michael Hachenberg, explained that the company could no longer keep its personnel and equipment earmarked for the project on standby.
Also read, More facts about NDDC’s Ugbo -Oghoye Road procurement report raises questions over contractors’ capacity and N19.5bn Adjusted Bid
https://exponentnews.com.ng/2026/11/12/more-facts-about-nddcs-ugbo-oghoye-road-procurement-report-raises-questions-over-contractors-capacity-and-%e2%82%a619-5bn-adjusted-bid/
The company also disclosed that its original tender submission, dated November 14, 2008, was valued at ₦39,708,015,078.80, significantly higher than the ₦19,409,143,685.70 subsequently approved by the commission.
The difference between the original tender sum and the approved contract amount was approximately ₦20.3 billion.
NDDC Technical Assessment Favoured Moreno Over Phomo
Following the development, another set of historical documents revealed that NDDC engineers conducted technical and capacity assessments of shortlisted contractors, including Phomo Nigeria Limited and Moreno DC West Africa Plc.
The assessments examined the companies’ technical personnel, construction equipment, management structures, financial and operational capacity, completed projects and ongoing construction activities.
A technical assessment of Phomo Nigeria Limited raised concerns about the company’s operational capacity, particularly its dependence on one individual, the Managing Director, and its inability to present the necessary construction equipment during the inspection.
The report stated that the plants and equipment identified at the company’s project sites were obsolete and non-functional.
It further disclosed that an ongoing road construction project had reportedly been abandoned following alleged non-payment by a state government, while its building project at Covenant University, Ota, Ogun State, which was said to have attained approximately 60 per cent completion, had also been stopped.
The assessment team equally observed that, apart from Engineer Olajide Adetayo, other professional personnel listed in the company’s profile were not presented during the inspection.
Only a few staff members were reportedly seen at the company’s office.
In its recommendation, the team acknowledged that the Managing Director of Phomo appeared to possess the technical knowledge required to execute engineering projects, including the Ugbo–Oghoye Road.
However, it expressed reservations about the company’s organisational structure and its inability to provide the necessary construction equipment.
The report described the company’s proposal to procure the required machinery after receiving a letter of contract award as risky.
Also read: Ugbo -Oghoye Road: Former NDDC Commissioner Enikuemehin Challenges Successors to Explain 15 Year Delay https://exponentnews.com.ng/2026/11/09/ugbo-oghoye-road-former-nddc-commissioner-challenges-successors-to-explain-15-year-delay/
It warned that relying on between 15 and 30 per cent of the contract sum as mobilisation funding to acquire construction equipment could jeopardise the successful execution of the project.
Moreno’s Equipment and Personnel Received Commendation
In contrast, a capacity and facility assessment conducted on Moreno DC West Africa Plc presented a more favourable picture of the company’s technical and operational capabilities.
The inspection, conducted by NDDC engineers in Lagos between March 30 and 31, 2010, was undertaken at the instance of the Executive Director of Projects to ascertain the company’s readiness and capacity to execute the Ugbo–Oghoye Road project.
The assessment team comprised Engineer Telemaye Ekpoke, Technical Assistant to the Executive Director of Projects, and Kormane Fun-akpo Pere, Assistant Manager, Infrastructure-UIDW.
The report disclosed that Moreno had been operating in Lagos State for approximately three years and was executing 16 projects for the Lagos State Government, comprising two road projects and 14 building projects.
Among the projects inspected were the Tedi-Muwo-Ira-Mile 10 Road project, measuring 4.5 kilometres with 500 metres of bridge works, and the Adisa-Ajibulu Road project, involving four kilometres of road construction and a 300-metre bridge.
Also read, update :Amuwa Blames Contact Disputes , Contractors Capacity For Three -Year Delayhttps://exponentnews.com.ng/2026/11/11/ugbo-oghoye-road-amuwa-blames-contract-disputes-contractors-capacity-for-three-year-delay/
The inspection team also visited the Eric Moore Group of Schools construction project in Surulere, comprising 19 buildings, as well as a five-storey International Arbitration building at Lekki.
The report identified several construction equipment owned by the company, including piling rigs, 120-tonne cranes, pay loaders, concrete batching plants, an excavator, tippers and mobile concrete mixers.
It further stated that the equipment inspected at the various construction sites was relatively new and in good working condition.
On manpower, the company reportedly informed the inspection team that it had more than 52 technical personnel across its engineering operations, with approximately 32 deployed to its Lagos projects.
The team also observed that the company’s ongoing projects were active, with construction work progressing at the sites visited.
It particularly noted that the terrain of the construction site at the Ariyo (Mile 10) Ira Abule Osun Road was similar to that of the Oghoye–Ugbo Road in terms of soil texture and vegetation.
The report added that inhabitants of the area attested to the nature of the terrain and the contractor’s ability to work under similar conditions.
NDDC Team Recommended Moreno for the Project
In its final recommendation, the technical assessment team described Moreno DC West Africa Plc as having a strong organisational structure, adequate resources and the technical capacity to execute projects of considerable magnitude.
The team consequently recommended the company for consideration for the construction of the Ugbo–Oghoye Road project.
The report was signed by Engineer Telemaye Ekpoke and Kormane Fun-akpo Pere.
The recommendation also noted that the company’s equipment was operational at the various construction sites inspected and that its technical personnel were available to execute projects of similar magnitude.
Olugbo Intervened in Contractor Selection
Further historical records revealed that the traditional ruler of Ugbo Kingdom, His Imperial Majesty, Oba (Dr.) Fredrick Eniti Obateru Akinruntan, intervened in the contractor selection controversy through a letter dated May 26, 2010.
The letter, addressed to the Director-General of the Due Process Office, Aso Rock Villa, Abuja, concerned the construction of the Ugbo–Oghoye Road by the NDDC.
In the correspondence, the Olugbo challenged a position reportedly presented by the then Honourable Member representing Ilaje/Ese-Odo Federal Constituency, Agboola Ajayi, who had allegedly objected to the consideration of Moreno DC West Africa Plc for the project.
The traditional ruler questioned the claim that the position represented the collective decision of stakeholders in the constituency, insisting that he was unaware of any stakeholders’ meeting convened to discuss the contractor selection.
Oba Akinruntan disclosed that he had consulted the Ondo State representative on the NDDC Board and the Chairman of the Ondo State Oil Producing Areas Development Commission (OSOPADEC) concerning the matter.
According to him, he was informed that both organisations had deployed technical teams to inspect Moreno’s construction sites and equipment yards.
He said the teams were satisfied that the company possessed the necessary resources and technical capacity to execute a project of such magnitude, particularly in challenging terrain.
The monarch further stated that he had examined photographs and videos presented as evidence of the company’s capabilities and found them convincing.
He consequently expressed support for Moreno’s consideration for the project, urging the relevant authorities to award the contract to the company without further delay.
The Olugbo also alleged that political interests were being introduced into the contractor selection process, describing the petition against Moreno as detrimental to the interests of the oil-producing communities.
He further claimed that, among the 44 mega projects awarded by the NDDC in 2009, projects in Ondo State had reportedly been stalled over issues surrounding the contractor selection process.
The traditional ruler appealed to the Federal Government’s Due Process Office to ensure that the Ugbo–Oghoye Road was not turned into a political subject by individuals pursuing personal interests.
Mimiko Flagged Off Project in December 2010
Historical photographic records have also established that the Ugbo–Oghoye Road project was formally flagged off on December 16, 2010, by the then Governor of Ondo State, Dr Olusegun Mimiko.
The flag-off ceremony, organised by the NDDC in collaboration with Moreno Group, took place at the project site in Ugbonla, Ilaje Local Government Area.
According to a 22-page historical photographic album documenting the event, the ceremony attracted government officials, traditional rulers, community leaders, political stakeholders and other dignitaries.
The programme identified Dr (Rev.) Benson Enikuemehin, the Ondo State representative on the NDDC Board at the time, as the chief host, while Nicola Busacca was listed as the Managing Director and Chief Executive Officer of Moreno Group.
Photographs from the ceremony showed the presence of heavy-duty construction equipment, including trucks and road construction machinery, at the project site.
The event also featured an inspection of the project area, interactions among dignitaries and addresses by key participants.
The flag-off represented a significant milestone in efforts to improve road infrastructure and connectivity in the riverine communities of Ilaje Local Government Area, particularly communities along the Ugbo–Oghoye axis.
Documents Raise Questions About Project’s History
The historical records provide important insight into the early contractual arrangements, technical evaluations and political disagreements surrounding the Ugbo–Oghoye Road project.
They also raise questions about the circumstances surrounding the initial contract award to Setraco Nigeria Limited, the company’s subsequent rejection of the offer, the technical recommendation of Moreno DC West Africa Plc and the eventual flag-off of the project in December 2010.
However, the available documents do not independently establish the final contractual arrangements with Moreno, the precise terms of any subsequent contract award, the payments made, the volume of work executed or the specific circumstances responsible for the prolonged delay in the project’s completion.
The revelations have renewed attention on the over-a-decade-old road project, particularly against the background of growing concerns among residents of the oil-producing communities over infrastructure development, accountability and the need for the completion of critical road projects in the riverine areas of Ondo State.
For the people of Ugbo, Oghoye and other neighbouring communities, the road remains a critical infrastructure project whose completion is expected to improve transportation, economic activities and access to essential services.
The historical records have therefore brought the project’s complicated history back into public discussion, with renewed calls for transparency and explanations from the relevant authorities over what happened to a project formally flagged off in 2010. The politics being played by the authorities concern in the delay of the Ugbo -Oghoye NDDC road project from materialization serve as the last straw that breaks the Camel’s back for the stalled of the project for a very long time and Ilaje people were not happy about this development.